Pre-Solicitation Conference June 24, 2025 – Materials

The Washington County Water Conservancy District (district) conducted a  pre-solicitation conference for design engineering for the Regional Reuse Purification System (system) conveyance components (project) on Tuesday, June 24, 2025.  Materials from the conference are now available online. 

The conference included a presentation on the project and multiple-award procurement process with an opportunity for questions and answers. Project information and scope are below.

Any questions regarding the materials available for download please contact Dinah Neumann at dinah@wcwcd.gov .

Project Information:

The system is a planned infrastructure network comprised of reclamation facilities, advanced water purification technology, conveyance infrastructure, and storage facilities. The district will be issuing a multiple-award procurement to solicit statements of qualifications for the design engineering of the conveyance components of the system.

Project Scope:

  • Approximately 37 miles of 48” welded steel pipeline
  • Three pump stations
  • Two storage facilities
Consultant(s) Dinah F Neumann
Open June 27, 2025
Close December 31, 2025 12:00 am
Vendor(s) n/a

Contact & Planholders List

Sign up to be added to the contact or plan holders list to receive addenda and revisions, project notifications and other project information.

Public Notice

Public Notice - Pre-Solicitation Conference Materials Available Online

Pre-Solicitation Conference June 24, 2025 – Materials

The Washington County Water Conservancy District (district) conducted a  pre-solicitation conference for design engineering for the Regional Reuse Purification System (system) conveyance components (project) on Tuesday, June 24, 2025.  Materials from the conference are now available online.

The conference included a presentation on the project and multiple-award procurement process with an opportunity for questions and answers. Project information and scope are below.

Any questions regarding the materials available for download please contact Dinah Neumann at dinah@wcwcd.gov .

Project Information:

The system is a planned infrastructure network comprised of reclamation facilities, advanced water purification technology, conveyance infrastructure, and storage facilities. The district will be issuing a multiple-award procurement to solicit statements of qualifications for the design engineering of the conveyance components of the system.

Project Scope:

  • Approximately 37 miles of 48” welded steel pipeline
  • Three pump stations
  • Two storage facilities

Project Documents and Information